Airfield Construction 2022

10.15.2019 9:10am local (by: MRL)

WEST SIDE AIRFIELD RAMP/TAXILANE WIDENING
COMPLETED 10.18.2019
Project Start Date: Monday, October 07, 2019
Project Cost: ~$190,000.
Project General Contractor: Meyers Earthwork, Inc.
Project Estimated Completion Date: October 25, 2019
Project Description: This project entails widening ramp/taxilanes along the western perimeter of Papa hangar row, the eastern edge of November hangar row, and southern perimeter of Mike, November and Papa hangar rows by 12.5'. This project will also square off the far western corner of the ramp at the Lima hangar row. The ramp/taxilane widening projects will ease aircraft maneuverability, allow for safer wing tip clearances, and also help facilitate snow removal.
Impacted Areas:
- All work to be done off the asphalt surfaces, with minimal to no aircraft impact.

10.2.2019 3:58pm local (by: MRL)

Maintenance Shop and Adjacent Generator Building Painting
COMPLETED 9.20.2019
Project Start Date: Monday, September 9, 2019
Project Cost: $16,705.32
Project General Contractor: Easterbrook Painting, Inc.
Project Completion Date: September 20, 2019
Project Description: The project entailed, prepping, priming and painting the airport's metal clad maintenance shop and adjacent generator building on the corner of Chandelle Way and Aviation Way.
Impacted Areas:
- No public areas will be impacted. Easterbrook Painting, Inc. will divide the job into sections allowing airport staff uninterrupted 24-7 access to the maintenance shop building and adjacent generator building.

8.27.2019 4:12pm local (by: MRL)

SAW CUT & SEAL SUPPLEMENTAL JOINTS, HANGAR TAXILANES J & K
COMPLETED 10.9.2019
Project Estimated Start Date: Monday, September 30, 2019
Project Cost: $90,000.
Project General Contractor: Q&D Construction
Project Estimated Completion Date: Friday, October 11, 2019 Schedule is weather and temperature dependent.
Project Description: Project involves cutting patterned expansion joints in existing asphalt taxilanes and filling with rubberized crack filler/sealer. This process extends the life of the asphalt.
Impacted Areas:
- During day light hours, (7am - 5pm) there will be intermittent day long hangar access restrictions to rows Juliet and Kilo.
- Care Flight helipad operations will temporarily be moved on a daily basis during impacted construction days.
- Vehicle access to hangars tenants in Lima, Mike, November and Papa may require temporary airfield access via the temporary gate in the warehouse parking lot. Follow traffic re-routing signs.

8.2.2019 2:09pm local (by: MRL)

Terminal Building East Side Parking Lot & Gate 7 Area Trenching
COMPLETED 10.11.2019
Project Start Date: Monday, August 5, 2019
Project Cost: Included in Taxiway Romeo Reconstruction FAA AIP Grant $1,900,000.
Project General Contractor: Meyers Earthwork, Inc.
Project First Phase Estimated Completion Date: Wednesday, August 14, 2019 (includes rough patching)
Project Description: Utility communication line upgrade
Impacted Areas:
- Terminal building east side parking lot will be closed, as well as Gate 7 by the playground for the week.
- Terminal building handicap parking, the receiving dock and the playground will remain open.
- Public parking will be condensed to the terminal west side parking lot with overflow on Chandelle Way if needed.
- Access to Sierra Aero, Mtn Lion, the tower, CAP and EAA will be thru Gate 5 (by the fire station and blast fence) via Air Show Way (road on south side of hangar rows Alpha thru Hotel)
* Caution yield to aircraft taxing on Air Show Way during construction.
* Caution construction vehicles will also be using Gate 5.
- The trench area will be temporarily patched until later in the taxiway Romeo project.

7.9.2019 3:20pm local (by: MRL)

HANGAR 1 OFFICE BUILDING
COMPLETED 12.31.2019
Project Start Date: Week of June 24, 2019
Project Cost: $600,000.
Project General Contractor: Prosser Building & Development, Inc.
Project Estimated Completion Date: December 31, 2019
Project Description: The project entails building a 1,920 sq ft office building to house: 2 offices, a reception desk, 2 bathrooms, a break room and a flight training room. In stage two of this project the 1960's era office space currently inside the hangar will be removed to expand hangar floor space to enable more planes to be under roof during maintenance service.
Impacted Areas:
- The dirt area on the west of Hangar 1.
- The Jetway Taxiway to the west of Hangar 1 will be closed during construction.

7.8.2019 11:17pm local (by: MRL)

HANGAR ROW BRAVO ROOF REPAIR
COMPLETED 07.21.2019
Project Scheduled Start Date: Week of July 8, 2019
Project Cost: Warranty work
Project Contractor: Summit Roofing
Project Duration: 1-2 weeks
Impacted Areas:
- There should be no impacted areas, other then some light duty construction vehicles and ladders around the Bravo row of hangars.
- An elastomeric roofing paint was applied in the summer of 2017. Some surfaces were not prepared properly and were seen to be peeling by airport O&M staff. TTAD contacted the roofer to fix the issue per the warranty agreement.

6.3.2019 10:34am local (by: MRL)

RUNWAY CLOSURES FOR RE-STRIPING
COMPLETED 6.14.2019
Project Scheduled Start Date: Week of June 10, 2019
Project Cost: $125,000.
Project General Contractor: Maxwell Asphalt
Project Duration: 1 week
Impacted Areas:
- Runway 2-20 will be CLOSED for 1 day (scheduled for Tues., June 11th weather permitting)
- Runway 11-29 will be CLOSED for 1 day (scheduled for Wed., June 12th weather permitting)
- There will also be miscellaneous short term taxiway and ramp closures during striping work.

5.6.2019 8:00pm local (by: MRL)

TAXIWAY ROMEO RECONSTRUCTION
COMPLETED 10.14.2019
Project Start Date: Monday, July 22, 2019
Project Cost: $1,900,000.
Project General Contractor: Meyers Earthwork, Inc.
Project Estimated Completion Date: Friday, October 18, 2019. Phase 1) 7/22/2019 - 9/13/2019, Phase 2) 09/18/2019 - 10/14/2019.
Project Description: Utility line replacement, and asphalt taxiway regrade, base and pave
Impacted Areas:
- Project will be done in two phases. Phase 1 will impact hangar tenants from Alpha hangars to Foxtrot west side 7/22/2019 - 9/13/2019. Phase 2 will impact hangar tenants from Foxtrot east side hangars to Hotel row. Construction will cause closure of the south end of parallel taxiway Golf, requiring back-taxi on Rwy 02 from taxiway Quebec. Work scheduled for 9/18/2019 - 10/18/2019.
- 175 hangar row tenants from the east side of Alpha hangar rows all the way to the Hotel row of hangars will be impacted by this major airfield project
- No alternate hangars are available
- Aircraft with a wingspan <39' (at pilot's discretion and own risk) can taxi on the south side of the hangar rows with Ground Control advisories on 118.3 MHz.
- Please note that obstacles exist.
- Aircraft on floats have not been verified as able to taxi on the south side of the hangars,
- Vehicle traffic must be cautious of taxiing aircraft and always give right of way. Max speed limit 15mph
- Outside ramp parking will be made available for any aircraft/pilots not able or comfortable taxiing on the south side of the hangars

5.6.2019 9:28am local (by: MRL)

HOTEL HANGAR ROW, H1 through H4 ROOF REPLACEMENT
COMPLETED 07.19.2019
Project Start Date: Tuesday, June 4, 2019
Project Cost: $390,000.
Project General Contractor: Garland/DBS, Inc.
Project Estimated Completion Date: Friday, June 28, 2019 (due to weather, rain at start and high winds) now scheduled for 7/19/2019.
Impacted areas:
- Hotel row hangars 1-4 (tenants will be displaced)
- No restrictions to taxiing aircraft traffic is expected
- Construction materials, vehicles and equipment storage will be on the east side of the hotel row


5.3.2019 2:53pm local (by: MRL)

HANGAR 1 - SEWER LINE INSTALLATION (replaces existing septic tank w/ a gravity feed sewer line)
COMPLETED 6.14.2019
Project start date: Tuesday, May 07, 2019
Project cost: $240,000.
Project General Contractor: Sierra Nevada Construction., Inc.
Project Estimated Completion Date: Friday, June 7, 2019
Impacted areas:
- Jetway closure (taxilane between Hgr 1-westside and the old Hgr 2 area)
- Gate 7 access may at times be restricted (use gate 5 - Air Show Way by the fire station as an alternate)
- Vehicle Parking: parking stalls airside of gate 7 will be closed during construction, and employee gravel lot will be at times restricted
- Construction materials, vehicle and equipment storage will be in the gravel lot west of the Jet Ramp