Taxiway Romeo Construction
Sep 30, 2019
TAXIWAY ROMEO SUMMER 2019 CONSTRUCTION
Phase 1 - Impact to hangar tenants in Alpha through Foxtrot west side. Scheduled dates of work 7/22/2019 - 9/13/2019.
Phase 2 - Impact to hangar tenants in Foxtrot east side through Hotel. Scheduled dates of work 9/18/2019 - 10/18/2019.
For the latest airfield construction news visit: https://truckeetahoeairport.com/aviation/construction
Aircraft with a wingspan <39' (at pilot's discretion and own risk) can taxi on the south side of the hangar rows with Ground Control advisories on 118.3 MHz. Please note obstacles exist. Arrows indicate traffic for aircraft exiting hangar rows. Be aware of aircraft and vehicle traffic on the south side of hangar rows during construction.